Cold bridging at window and door reveals is stopped by carrying insulation right up to the frame, closing the cavity with an insulated closer, and sealing the frame to the wall so air can’t get round it. Get that wrong and you’ll see condensation, mould at the jambs and a thermal bridging bill on the SAP calculation that doesn’t match what you built. Here are the questions that come up most on site, answered straight.
Why do window reveals cause cold bridging?
Reveals cause cold bridging because the inner leaf, the outer leaf or the cavity closer meets the frame at the one place where the wall build-up is interrupted. Heat takes the easiest route out, so a bare block return, a cavity left open or a gap round the frame becomes a line of cold surface. That’s where condensation settles first, usually at the jambs and the cill.
Part L of the Building Regulations (Conservation of fuel and power) expects junctions to limit heat loss and avoid surface condensation and mould. The approved documents point to the junction details published by the government, and to calculated psi-values where you are not using those. Either way, the inspector wants to see what’s actually in the wall, not what the drawing says.
What reveal depths should you plan for?
On a typical cavity wall, plan for a frame that sits within the insulation zone, with a reveal return of roughly 90 to 100mm of outer leaf showing and the frame lapping the cavity edge. The exact figure depends on your wall type and how far the frame sits back from the face, so work it out from the drawings before the openings are formed.
The mistake I see most is setting out the openings to the brick and the joinery to a different dimension. If the frame sits proud of the insulation line, you’ve got a gap with no room for a closer or a sealant joint. Sort the frame position at first-fix stage, not when the window turns up.

What insulation options work at reveals?
The main options are insulated cavity closers, thin rigid insulation boards on the return, and a thermally broken lintel and cill. Each does a different job, so you often need two of them together.
| Option | Where it goes | Watch for |
|---|---|---|
| Insulated cavity closer | Vertical cavity edge at jambs | Fit tight to the frame, no gaps at the corners |
| Rigid PIR or phenolic board | Inner reveal return | Thin boards still need taping and plastering to a clean edge |
| Thermally broken lintel | Head of opening | Steel lintels with no break are a classic weak point |
| Insulated cill or cill board | Base of opening | Check it meets the DPC and cavity tray |
On external wall insulation jobs the same principle applies: wrap the insulation onto the reveal so the frame is overlapped. Our guide to EWI specification, fixing and failures covers the return detail in more depth.
What are building control officers flagging in 2026?
Building control officers are mostly flagging the same site-level problems: missing or poorly fitted cavity closers, no photographic record of the detail before it’s covered, and frames set outside the insulation line. These are things you can fix in minutes before the plasterer arrives and can’t fix at all afterwards.
Since the 2022 uplift to Part L, inspectors have also been looking for evidence that the as-built junctions match the thermal bridging assumptions in the SAP or SBEM calculation. If your designer used the accredited details, you need to build to them. If you’ve swapped a product, tell the designer so the numbers can be rerun. Our wider piece on cold bridging in new builds and extensions explains how to spot the problem across the whole building.
How do you seal the frame against air leakage?
You seal the frame with a continuous airtight layer: expanding foam or a low-expansion foam in the gap, then an internal sealant or airtight tape lapped onto the wall finish, plus a weather-resistant seal outside. Foam alone is not an air barrier you can rely on.
Remember ventilation. A tighter envelope changes how a house breathes, so check trickle vents and extract rates against Part F ventilation requirements.

Do you need machinery to get reveals right?
You don’t need much, but accurate joinery helps. Where carpenters make their own window boards, reveal linings and bespoke frames, clean, square, repeatable cuts mean tighter fits against the insulation. International Woodworking Machinery Ltd, a Newark, Nottinghamshire firm that supplies woodworking machinery to joiners and builders (iwmachines.co.uk), is one source for the planers, saws and moulders that in-house joinery shops use for that sort of work.
For site carpenters on new builds, tight tolerances at the opening matter more than any gadget. A frame that is a few millimetres out leaves a gap that foam and sealant then have to hide.
A site checklist before the plasterer arrives
- Confirm the frame position against the drawing and the insulation line.
- Check cavity closers are continuous and tight at every corner.
- Photograph the head, jambs and cill before they are covered.
- Seal the frame to the wall inside and out.
- Check the lintel is the thermally broken type specified.
- Tell the designer about any product change, then keep the paperwork for the completion file.
Keeping those photos and notes also helps at handover, as explained in our guide to the practical completion certificate. For the regulation itself, the government’s Approved Documents page is the place to check the current Part L wording.