A span table will size a joist for a plain domestic floor, and it will do it faster and cheaper than an engineer. It will not size a joist for your job if your job isn’t the one the table was written for. Most bad joist calls come from that gap, not from misreading a number. Here is how floor joist span tables work under UK building regulations, and where to stop.
The tables you’ll meet are the TRADA span tables, which are widely used for domestic timber, and the tables in the Approved Documents and the standards they point to. Check with your building control body which source they accept on your job. Whichever you use, the logic is the same.

What a floor joist span table actually tells you
A floor joist span table gives you the maximum clear span for a joist of a given size, strength class and spacing, under a stated load. Run it backwards and it tells you the smallest joist that will do the job for the span you have.
Four inputs drive the answer: the timber grade, the joist depth (and width), the centre spacing, and the span. Change any one and the other three have to move with it.
How to read the four variables
Grade
Softwood joists are sold by strength class, most commonly C16 and C24. C24 is stronger, so for the same section and spacing it spans further. Check the stamp on the timber. If the table is for C24 and your merchant has delivered C16, the table no longer applies to what is on your site. C16 is the usual default on many domestic jobs, which is why the grade is worth confirming before you order, not after.
Depth and width
Depth does most of the work. Stiffness rises steeply with depth, so going from a 147 mm to a 195 mm joist buys far more span than adding width. Sizes in tables are usually the regularised (planed) dimensions, so a nominal 8 x 2 is not what you will be holding. Read the table’s size, not the timber yard’s label.
Spacing
Centres of 400 mm and 600 mm are the common columns. Closer spacing shares the load across more joists and lets you span further or drop a size. Check it against your board: standard chipboard and similar flooring is generally laid for 400 or 600 mm centres depending on thickness, so confirm what your decking needs before you pick wider spacing to save timber.
Span
This is the one people get wrong. The span in the table is the clear distance between supports, not the length of the timber. Measure from the inside face of one bearing to the inside face of the next, and read the table for that figure or the next one up. Never round down.
How do you size a joist from the table?
To size a floor joist, follow these steps in order:
- Measure the clear span between supports.
- Confirm the load category: a standard domestic floor, with or without a partition sitting on it.
- Pick the strength class you can actually buy and check it is stamped.
- Choose the spacing your floor boarding allows.
- Read across to the smallest depth whose permitted span is equal to or longer than yours.
- Check bearing length and any notches or holes against the rules.
Say you have a 3.6 m clear span at 400 mm centres in C24. You find 3.6 m, or the next figure above it, in the C24 and 400 mm column, and read off the section that covers it. If it falls just short in one depth, go up a depth. Don’t squeeze it.
What the table assumes, and what breaks it
Tables carry stated loads, typically an imposed floor load and a dead load for the structure. They assume plain joists, evenly spaced, bearing properly at both ends. That covers a lot of ordinary floors. It does not cover:
- Walls built off the joists, especially load-bearing ones or a bath full of water on a thin floor.
- Heavy finishes such as a stone floor or a deep screed, where the dead load goes beyond the table’s allowance.
- Notches and holes cut for pipes and cables, which are limited by rules on where and how big.
- Trimmed openings for stairs, hatches and chimneys, where trimmer and trimming joists carry the load of others.
- Joists carried on a new steel or on a wall you have altered.
- Unusual spans, or a floor that must also meet a stiffness or sound requirement.
Most of those are exactly where the weight concentrates. Tables cover uniform loads, and point loads are the engineer’s territory.
When to stop and call a structural engineer
Call a structural engineer when the load is not uniform, when the span exceeds the table, or when joists bear onto something new. A loft conversion, a first-floor extension with a bearing wall above, or a floor carrying a wet room all fall into that bracket. If you have to adapt the table to make it fit, it doesn’t fit.
Building control will usually want calculations for anything outside standard tables. Having those drawn up costs far less than lifting a floor after a failed inspection. If you are weighing joist types first, our piece on I-joists versus C16 timber joists covers the choice, and the beam and block versus suspended timber comparison helps at ground floor level.
Where to check the rules
Structural requirements sit in Approved Document A, which you can read on GOV.UK’s Approved Documents page. Building regulations are set separately in Scotland, Wales and Northern Ireland, so check the version that applies to your site.
Before you order, ring your building control officer, tell them which table you’ve used and the numbers you’ve read from it, and ask if they’re happy. A five-minute call beats a week of rework.