  • Air Pressure Testing on New Builds: How to Pass First Time

    Air Pressure Testing on New Builds: How to Pass First Time

    Air pressure testing is a standard requirement for new dwellings in England and Wales because Part L of the Building Regulations sets a limit on how much air a new home can leak, and the only way to prove you have met it is to measure it. A test result at or below the limit gets you the paperwork for sign-off. A fail means remedial work, a retest and a delay.

    This guide covers what the test measures, what the score means, and the steps I’d follow on site to avoid a fail.

    What is air pressure testing and who does it?

    Air pressure testing, also called airtightness or blower door testing, measures how much air leaks through the building fabric when the house is pressurised and depressurised to 50 pascals. A fan is fitted into an external doorway, all planned openings are closed or sealed, and the tester records how much air the fan has to move to hold that pressure difference.

    The test has to be carried out by a competent person. In practice that means a tester registered with a scheme such as the British Constructors Testing Association or an equivalent body, using calibrated equipment. You can’t test your own plot and submit the figure. Building control will want the certificate, and for new dwellings, Part L sets out sample testing arrangements for developments, with the details in the approved document.

    The test is done when the building is substantially complete, with the air barrier finished but before you’ve buried problems under finishes you’d need to rip out. Book your tester early, because good ones get booked up.

    Blower door fan fitted in a new-build doorway during air pressure testing
    Photo by Roman Ska on Pexels

    What does an airtightness score actually mean?

    An airtightness score is the air permeability of the dwelling, shown in cubic metres of air per hour per square metre of envelope area at 50 pascals (m³/h·m² @ 50Pa). A lower number means a tighter house. The design figure comes from the SAP calculation for the plot, and the measured result has to be at or better than the figure used there, and within the limiting maximum set in Part L.

    Check the current approved document for the exact limiting value, as it has changed with revisions. The point on site is simple: the SAP assessor has assumed a number, and if you land above it, the plot’s energy performance no longer works on paper. You’d then need to fix the leaks or rework the specification with extra measures elsewhere, which usually costs more.

    A tighter house also needs proper ventilation. Part F still applies, so see our guide to Part F ventilation requirements for what has to go in once the shell is sealed.

    How to prepare for the test: step by step

    1. Agree the air barrier line before you start. Decide whether it’s wet plaster, a taped membrane or boards, and mark it on the drawings. Every trade should know where the line runs. If nobody knows where it is, it will have gaps.
    2. Seal service penetrations as they go in. Pipes, cables, flues, extract ducts and soil stacks are the biggest cause of failures. Use proper grommets, tape or sealant around each one, and seal behind boxed-in pipes before the boxing goes on. A gap round a soil pipe in a bathroom wall can leak all day.
    3. Deal with window and door reveals. Seal the frame to the wall, not just the frame to the plasterboard. Use an airtight tape or a continuous bead of sealant, and make sure plaster meets the frame without gaps. Cold bridging and air leakage often happen at the same detail, so read our piece on cold bridging at window reveals alongside this.
    4. Fit an airtight loft hatch. A standard hatch with a loose lid is a hole in the ceiling. Use a hatch with a compression seal and a positive catch, and seal the frame to the ceiling lining.
    5. Check sockets, spotlights and ceiling fittings. Back boxes in dry-lined walls need dabs or sealed boxes, and recessed downlighters in the top-floor ceiling need to be rated for airtightness or avoided.
    6. Look at the junctions. Wall to floor, wall to roof, party wall heads and the eaves are where plaster stops and gaps hide. Seal the gaps around joist ends and wall plates.
    7. Do your own walk-round before the tester arrives. Close all windows and doors, then check for draughts with a smoke pencil on a windy day. Fixing a few gaps before the test is cheaper than paying for a retest.
    Builder sealing around a pipe penetration in a wall
    Photo by – Manouar on Pexels

    Which mistakes cause most failures?

    The same few details come up again and again. Service penetrations are top of the list: pipes through floors into the void, extract fans, and cables through top plates into the loft. Window reveals come next, especially where the frame has been fixed but the gap behind the plaster is left open. Loft hatches round it off, because they’re fitted last and sealed least.

    Other common culprits are unsealed gaps at the base of stud walls on the external line, open ends of hollow party walls, and the boxed-in areas behind kitchen units and bath panels. Most of these are trade-sequence problems. The plumber, the electrician and the carpenter all make holes, and nobody owns sealing them. Give one person the job of checking the air barrier before the plasterboard goes on.

    What happens if you fail?

    If the dwelling fails, the tester will usually help you find the leaks while the fan is running, using smoke or a hand to feel for moving air. You fix the leaks and retest. Some testers charge for a second visit, and building control won’t sign off until a passing certificate is in hand, so a fail can hold up completion and legal handover.

    Where good detailing starts

    Airtightness is much easier to achieve if the design is simple and the details are drawn properly. If you’re a small builder winning more new-build or self-build work, a clear online presence helps you show clients you take quality seriously, and a firm like dijitul Web Design can help get your portfolio of finished, certified projects in front of them. On site, though, the work comes down to sealing every hole and keeping a continuous line.

    For wall construction, the cavity wall construction guide covers the build-up that sits behind your air barrier. Check the current Part L approved document on GOV.UK for the limiting air permeability, and book your tester before the plasterers finish.

    Frequently Asked Questions

    Is air pressure testing mandatory for all new homes?

    For new dwellings in England and Wales, air pressure testing is required to show compliance with Part L. Developments of several identical plots can follow sample testing rules set out in the approved document. Check with your building control body which approach applies.

    How long does an air pressure test take?

    A typical test on an average house takes around an hour to an hour and a half, including set-up. Time varies with the size of the property and how many leaks need tracking down. Allow longer if you want help locating failures.

    Can I retest if my house fails?

    Yes. Once you have sealed the leaks, you can book a retest. The tester will run the procedure again and issue a certificate if the result meets the design figure. Some testers charge a fee for return visits.

    Do extensions need an air pressure test?

    Extensions to existing homes generally aren’t subject to the same air pressure testing requirement as new dwellings. They still need to meet Part L standards for the fabric, so good sealing is worth doing anyway. Check with your building control officer.