Say you have finished first fix on a two-storey extension. The plumber has run pipes through the party wall, the sparky has drilled through every joist, and the Building Control inspector turns up for the pre-plaster visit. He looks at a soil pipe through the floor with a gap round it you could post a letter through, and the visit is over. That is fire stopping, and it is one of the commonest reasons for a failed inspection. In short: fire stopping in walls, floors and roof voids means sealing every gap and penetration in a fire-resisting element with a tested product, so fire and smoke cannot pass through.
The rules sit in Approved Document B (Fire safety, Volume 1: Dwellings) under the Building Regulations 2010 for England. Wales, Scotland and Northern Ireland have their own versions, so check which applies to your site.
What needs fire stopping on a domestic build?
Any opening, joint or penetration through a wall, floor or cavity barrier that is meant to resist fire needs sealing to the same standard as the element it passes through. On a typical house that means:
- Party walls between semis and terraces, including the top of the wall at the roof line.
- Floors between a garage and the house, and floors in flats or loft conversions.
- Walls and floors around protected stairways, such as the enclosure to a loft conversion escape route.
- Cavity barriers at the edges of cavities and at the junction of a cavity wall with a separating wall or floor.
- Service penetrations: pipes, cables, ducts and recessed fittings in any of the above.
Roof voids catch people out. A separating wall must continue up to the underside of the roof covering, and the gap between wall and roof structure at eaves and ridge needs stopping with a suitable material.

How to fire stop a penetration, step by step
- Identify the fire-resisting element. Check the drawings and the Building Control notes. You cannot pick the right product until you know the rating needed, usually 30, 60 or 90 minutes depending on the element.
- Keep the hole small. Drill or cut to suit the service. A tight opening is easier to seal and less likely to fail. Oversized holes in joists also upset structural checks.
- Choose a tested product. Use one with test evidence for your exact situation: the type of pipe, the substrate, the gap size. Check the manufacturer’s data sheet, not just the tub label.
- Match the product to the service. Plastic pipes (soil, waste) need an intumescent collar or wrap that crushes the pipe as it melts. Metal pipes usually need mineral wool and sealant. Cables need intumescent sealant, putty or a pass-through system.
- Install to the instructions. Depth of fill, collar fixings and sealant bead size all matter. A thin skim of mastic over an empty void will not pass.
- Label and photograph. Take dated photos before boarding over. Many inspectors want evidence of what is behind the plasterboard, and it protects you later.
- Book the inspection before closing up. Once boards are fixed, you may be asked to open up.
Which products are approved for fire stopping?
Approved Document B says fire stopping materials should be proven by test to resist fire for the required period, or be a recognised material such as cement mortar, gypsum-based plaster, cement or gypsum-bonded sheet, or rigid mineral wool in the right circumstances. In practice, most domestic jobs use:
| Product | Typical use |
|---|---|
| Intumescent collars and wraps | Plastic pipes through floors and walls |
| Intumescent sealant or acrylic | Small gaps, cable penetrations, joints |
| Fire-rated mineral wool slabs | Larger gaps, around metal pipes, cavity closers |
| Intumescent pillows and putty pads | Back boxes, cable bundles |
| Cavity barriers | Cavity edges, roof eaves, wall heads |
Look for third-party certification, such as a UKCA or CE marked product with test evidence, or schemes like BM TRADA or IFC. Expanding foam from the DIY shelf is not fire stopping unless it is specifically a fire-rated product, and ordinary silicone is not either.

Common omissions that fail sign-off
Having seen the same snags on site over the years, I would check these before the inspector does:
- Gaps round soil pipes and waste pipes at floor level, especially in garage ceilings.
- Unsealed holes where electricians have run cable through party wall plasterboard or joists.
- Recessed downlights fitted in a fire-resisting ceiling without fire hoods or rated fittings.
- The party wall stopping short of the roof covering, leaving an open void at the eaves.
- Missing cavity barriers round window and door reveals, or at the top of a cavity wall.
- Wrong product for the pipe, such as mastic used where a collar is needed.
- No record of what was installed, so the inspector cannot confirm it.
Later trades are the main cause. A builder seals everything at first fix, then the heating engineer adds a new pipe run and nobody goes back. Tell every trade that new holes in rated elements need stopping by whoever made them.
Why inspectors are looking harder at fire stopping
Fire safety in buildings has had far more attention since the Grenfell Tower fire in 2017, and the Building Safety Act 2022 tightened accountability for higher-risk buildings. Most domestic jobs are not higher-risk buildings, but the attitude has filtered down. Inspectors ask more questions and want evidence, so assume your work will be looked at closely.
Getting the right fixings and finishing details
One more thing that trips people up is what goes on the wall after fire stopping. Any fixings you add later, such as brackets, cable clips or a bracket for a wall-mounted telly, can break the seal or the board if you drill through a rated wall carelessly. If you are fitting a screen on a party wall or protected stair enclosure, plan the cable route first, as a guide to tv-aerials.co.uk shows how cable routing and wall fixing work in practice. Any hole through the wall must be sealed back to the original rating.
For wider detail on the principles, see our earlier piece on what tradesmen must seal and why Building Control cares, and the guide to plasterboard types if you are unsure which board suits a fire-rated wall. The official detail is in Approved Document B on gov.uk. Before your next inspection, walk the job with a torch and a camera, tick off every penetration, and fix the gaps while the boards are still off.
Frequently Asked Questions
Do I need fire stopping on a single-storey extension?
Possibly. If the extension adjoins a party wall, or has a wall or ceiling that forms part of a fire-resisting element, openings in it need sealing. Cavity barriers may also be needed. Ask your Building Control body which elements are rated on your job.
Can I use expanding foam for fire stopping?
Only if the foam is specifically sold and tested as fire-rated for that gap and substrate. Standard expanding foam from a builders’ merchant is not fire stopping. Check the manufacturer’s data sheet and keep a copy.
What is the difference between fire stopping and a cavity barrier?
A cavity barrier closes a concealed cavity to stop fire and smoke spreading within it, such as at wall edges or eaves. Fire stopping seals gaps and service penetrations through fire-resisting walls and floors. Both are needed on many jobs.