Thermal Bridging and Part L: What Psi Values Mean on Site

·

,

The most common mistake is treating thermal bridging as a insulation-thickness problem. It isn’t. You can fit the thickest board on the market and still fail, because the heat escapes at the junctions: lintels, wall-to-floor edges, eaves and reveals. Get those wrong and the SAP calculation punishes you, whatever the U-values on the drawings say. This guide covers thermal bridging and Part L compliance for UK builders, in plain terms.

What is thermal bridging?

Thermal bridging is heat leaking through a part of the building envelope that conducts better than the insulated area around it. Think of a steel lintel running through a cavity wall, a concrete slab edge poking through to the outside, or timber studs where insulation stops. Heat takes the easy route, the inside face of that spot runs colder, and in a bad case you get condensation and mould there.

Two types matter. Repeating bridges, like studs or wall ties, are already counted inside the U-value of the element. Non-repeating (linear) bridges happen at junctions, such as where a wall meets a ground floor, and are calculated separately. Those linear ones are where small builders lose points.

What is a psi value?

A psi value (written as the Greek letter ψ) measures how much heat is lost along each metre of a junction, in watts per metre kelvin (W/mK). The lower the figure, the better the detail. Each junction in the house, such as the ground floor edge, window jamb, sill, head, eaves and gable, has its own psi value, multiplied by its length in metres.

Add all those up and you get the total heat lost through the junctions. A long run of poor detailing adds up fast on a simple extension.

Cavity wall under construction showing insulation and lintel, relevant to thermal bridging Part L compliance for UK builders
Photo by Mikael Blomkvist on Pexels

How do psi values feed into SAP calculations?

SAP, the Standard Assessment Procedure used by the government to assess the energy performance of dwellings, takes the length of every junction, multiplies by its psi value and adds the result to the fabric heat loss. The y-value is the total junction loss divided by the exposed area of the building. A higher y-value means a hungrier house on paper, and the rest of the design has to make up the difference.

There are three ways to get psi values into the calculation. You can use the default y-value, which is a penalty figure that assumes nothing about your detailing and is the worst option. You can use the SAP default psi values for named junction types, which is better but still generous to nobody. Or you can use calculated values or details from a recognised, certified construction details scheme, which gives the best figures and the best chance of passing without bolting on expensive extras like more PV.

The Approved Document L (conservation of fuel and power) sets out the compliance route, and the current version is on GOV.UK’s Approved Documents page. Your SAP assessor will tell you which figures they have used, so ask early.

What do small builders have to change on extensions and new builds?

The detailing changes are mostly about continuity: keep the insulation line unbroken from floor to wall to roof. In practice that means a handful of habits.

  • Lintels: use insulated or cavity-bridging lintels designed for the job, not a plain steel angle with the cavity closed round it.
  • Ground floor junction: bring the floor insulation up to meet the wall insulation, using a lower course of thermal blocks at the base of the wall where the design calls for it.
  • Window and door reveals: set frames within the insulation zone and return insulation onto the reveal. Our guide to cold bridging at window reveals goes through this.
  • Eaves and gables: don’t let the roof insulation stop short of the wall insulation. Leave no gap behind the wall plate.
  • Balconies and steel: thermal breaks on any element that passes through the envelope.

For the wider picture on spotting and fixing these on site, see our piece on cold bridging in new builds and extensions.

Do extensions need the same thermal bridging checks as new builds?

Extensions have to meet Part L for the new work, but you usually don’t produce a full SAP for the whole house the way you do for a new dwelling. Instead the building control body generally looks at the elemental U-values and the junction details, and the designer may use a calculation to show the extension complies. Either way, the junction details still need to be sound, and an extension adds more awkward joints because it meets an existing wall that you can’t always insulate.

The junction with the old building is the weak point. Where the old wall meets the new, work out on paper how the insulation line carries across before you start digging, not when you reach the corner.

How do you prove the details were built as designed?

Photograph everything before it’s covered up. Building control will ask for evidence that the junctions match the drawings, and a dated photo of the lintel, the cavity closer and the insulation at the eaves is far better than an argument afterwards. If you are using accredited details, keep the paperwork from the supplier with the job file.

Make sure the as-built SAP uses the details actually installed. If the bricklayer swapped a lintel to save a day, the figures change and the energy assessment has to be updated. Tell the assessor before the swap, not after the inspector spots it.

My advice: ask your SAP assessor for the junction list at design stage, pin it up on site, and tick each one off with a photo as it goes in.