Most damp callbacks are not caused by bad products. They come from the right product in the wrong place, or the right place with a lap left open. Damp proofing a UK build comes down to three products doing three separate jobs: a DPM stops moisture coming up through the floor, a DPC stops it rising or tracking through the wall, and a cavity tray catches water that gets into the cavity and throws it back out.

Mix those jobs up and you get the classic failures: a damp skirting, a stained lintel reveal, a patch on a ceiling below a chimney. Here is where each one belongs and how to get it past the inspector.

Cavity tray fitted above a window lintel in a brick and block cavity wall
Photo by Fotografías de El Puerto de Santa María on Pexels

What does each damp-proof product actually do?

A damp proof membrane (DPM) is a sheet or liquid layer that sits in the ground floor to stop moisture and, in some areas, radon gas coming up from the ground. A damp proof course (DPC) is a strip of flexible material built into a wall to stop moisture rising from the ground or passing sideways. A cavity tray is a DPC formed into a stepped or sloped shape that carries water out of the cavity through weep holes.

They are meant to be one continuous barrier. The DPM laps with the DPC, and the cavity tray ties into the DPC at lower levels. Gaps between them are where the water gets in.

How to place each product, step by step

  1. Ground floor slab or beam and block: the DPM. Lay the membrane, usually heavy-duty polythene, over well-blinded hardcore so nothing punctures it. Lap joints and seal them with tape. Then turn the edges up at the walls and lap them with the DPC. If you are putting insulation above or below the membrane, the position changes the detail, so settle it before you pour. The choice of floor itself is covered in our guide to beam and block versus suspended timber floors.
  2. Both leaves of the wall at ground level: the DPC. Build it in at least 150mm above finished ground level, which is the guidance in Approved Document C, and make sure it sits below the level of the floor DPM or is lapped to it. The DPC must run through the full thickness of each leaf, not stop short of the cavity face.
  3. Bridged cavities and the cavity base: keep it clear. Mortar snots and droppings at the bottom of the cavity can bridge the gap and carry water across to the inner leaf. Keep the cavity clear to below the DPC with a batten you lift as you build, and leave the cleaning holes or a clean-out course where the design needs it.
  4. Above openings: cavity trays over lintels. Fit a tray over every lintel that does not form its own barrier, with stop ends and weep holes at the outer leaf, commonly at no more than 900mm centres. The tray should fall to the outside, and the inner edge must rise above the lintel so water cannot run back into the cavity.
  5. Reveals, jambs and sills: vertical DPCs. At window and door reveals, a vertical DPC or insulated cavity closer stops damp crossing from the outer leaf to the inner. Sills need their own DPC below them, with the ends turned up.
  6. Abutments and roof junctions: stepped trays. Where a roof meets a wall, or at chimneys, use stepped cavity trays that follow the roof line and tie into the flashing, with weeps at each step.

Where do cavity trays go on a UK house?

Cavity trays go anywhere the cavity is bridged or interrupted: over lintels, above cavity-bridging door and window frames, below parapets, at roof abutments, around chimneys and at the junction where a flat roof meets a wall. Full detail on ties and insulation in the cavity is in our piece on cavity wall construction.

Remember that a cavity tray is only as good as its weep holes. A tray with the weeps buried behind a render bed or blocked with mortar simply holds water in the wall.

Misspecification mistakes that cause callbacks

The first is using DPM polythene where a DPC is needed, or the reverse. Thin sheet can tear or slip in a wall, and a proper DPC is built for the loads of masonry sitting on it. The second is a DPC that sits lower than the damp-proof membrane, so there is a gap in the line. The third is a DPC that is too close to the ground, usually after the landscaping goes in and raises the level. A patio laid at DPC height gives you a splash bridge.

Others I see again and again: no stop ends on cavity trays, so water runs sideways to the next unit; trays laid flat instead of falling to the outer leaf; and render or external insulation taken down over the DPC so moisture can track behind it. If you are fitting insulation to the outside of an existing wall, check the ground level and DPC position first, as covered in our guide to external wall insulation.

Timber near these barriers needs care too. Sole plates, wall plates and sill boards sit close to the DPC and need to stay dry and treated. Cut ends of pressure-treated softwood lose their protection and should be brushed with a preservative. If you cut and machine your own timber for that work, a workshop kitted out with planers and saws from International Woodworking Machinery gives you accurate sections that sit properly on a DPC without packers or gaps.

What do building inspectors look for?

Building control surveyors usually check damp proofing at specific stages, and it is far cheaper to be ready than to open up finished work. At foundation and oversite stage they want to see the hardcore blinded, the DPM laid without punctures, laps taped and edges turned up. At DPC level they look at height above ground, continuity round the whole building and laps with the membrane.

As the walls go up, they will look for cavity trays above openings, stop ends, weep holes and clean cavities. Take dated photos of anything that will be covered, such as trays behind brickwork and the DPM before the screed goes down. If the inspector cannot get there in time, photos are a useful record when you hand over.

The requirements themselves are set out in the Approved Documents, and Part C on site preparation and resistance to contaminants and moisture is the one to check, via the government’s Approved Documents collection. Always work from the version in force for your project and follow the manufacturer’s instructions for your specific product.

Frequently Asked Questions

What is the difference between a DPC and a DPM?

A DPC is a barrier built into a wall to stop moisture rising or passing through the masonry. A DPM is a membrane in the ground floor that stops moisture coming up through the slab. They must overlap so that the barrier is continuous round the building.

How high should a DPC be above ground level?

Approved Document C guidance is for a DPC to sit at least 150mm above finished ground level. This helps stop rain splashing up and bridging the barrier. Check the level again after landscaping, as raised paving often ruins it.

Do I need a cavity tray above every window?

You need one above any opening where a lintel or frame would otherwise let water cross the cavity, which in most masonry cavity walls means above windows and doors. Some lintels have their own integral tray. Follow the lintel manufacturer’s guidance and the design.

How far apart should cavity tray weep holes be?

Weep holes are commonly spaced at no more than 900mm centres, with at least two over a single opening. They must be open at the outer leaf and not blocked by mortar or render so water can escape.

When does building control inspect damp proofing?

Inspectors normally visit at foundation, oversite and DPC stages, then again as the walls rise. Agree the visit schedule with your building control body at the start, and keep dated photos of any work that will be covered up.